Upgrades to a WesTech Tri-Mite water treatment plant
Environmentally sensitive area
Improvements to an existing water treatment plant building
Project Summary
The water intake for MacKerricher State Park is located in Lake Cleone. Due to beach erosion, Lake Cleone is returning to its original state as a tidal lagoon. Because of the saltwater intrusion and excessive vegetation, a new water source is required. The project is intended to provide a new water source for the park and provide water treatment system upgrades.
Coleman Engineering has provided preliminary engineering and revision of the design of the two raw water intakes. The services included the Mill Creek Intake and Pump Station and Lake Cleone Pump House Improvements. A preliminary design memo and 50% draft plans have been successfully produced for the Department of Parks and Recreation.
Coleman Engineering was also been retained by the Department of Parks and Recreation to aid Environmental Consultants during the environmental review process.